A) $250.15
B) $277.94
C) $305.73
D) $336.31
E) $369.94
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $138.10
B) $149.21
C) $160.31
D) $171.42
E) $182.52
Correct Answer
verified
Multiple Choice
A) If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV.
B) If Project A's IRR exceeds Project B's, then A must have the higher NPV.
C) A project's MIRR can never exceed its IRR.
D) If a project with normal cash flows has an IRR less than the WACC, the project must have a positive NPV.
E) If the NPV is negative, the IRR must also be negative.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $185.90
B) $197.01
C) $208.11
D) $219.22
E) $230.32
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the risk-free rate, while the IRR method assumes reinvestment at the IRR.
C) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the risk-free rate.
D) The NPV method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
E) The IRR method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
Correct Answer
verified
Multiple Choice
A) Each project must have a negative NPV.
B) Since the projects are mutually exclusive, the firm should always select Project B.
C) If the crossover rate is 8%, Project B will have the higher NPV.
D) Only one project has a positive NPV.
E) If the crossover rate is 8%, Project A will have the higher NPV.
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method is that it does not take account of cash flows over a project's full life.
B) One defect of the IRR method is that it does not take account of the time value of money.
C) One defect of the IRR method is that it does not take account of the cost of capital.
D) One defect of the IRR method is that it values a dollar received today the same as a dollar that will not be received until sometime in the future.
E) One defect of the IRR method is that it assumes that the cash flows to be received from a project can be reinvested at the IRR itself, and that assumption is often not valid.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method versus the NPV is that the IRR does not take account of cash flows over a project's full life.
B) One defect of the IRR method versus the NPV is that the IRR does not take account of the time value of money.
C) One defect of the IRR method versus the NPV is that the IRR does not take account of the cost of capital.
D) One defect of the IRR method versus the NPV is that the IRR values a dollar received today the same as a dollar that will not be received until sometime in the future.
E) One defect of the IRR method versus the NPV is that the IRR does not take proper account of differences in the sizes of projects.
Correct Answer
verified
Multiple Choice
A) The internal rate of return method (IRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
B) The payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
C) The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
D) The net present value method (NPV) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
E) The modified internal rate of return method (MIRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
Correct Answer
verified
Multiple Choice
A) 14.05%
B) 15.61%
C) 17.34%
D) 19.27%
E) 21.20%
Correct Answer
verified
Multiple Choice
A) 2.03 years
B) 2.25 years
C) 2.50 years
D) 2.75 years
E) 3.03 years
Correct Answer
verified
Multiple Choice
A) 2.31 years
B) 2.56 years
C) 2.85 years
D) 3.16 years
E) 3.52 years
Correct Answer
verified
Multiple Choice
A) If a project's IRR is equal to its WACC, then, under all reasonable conditions, the project's NPV must be negative.
B) If a project's IRR is equal to its WACC, then under all reasonable conditions, the project's IRR must be negative.
C) If a project's IRR is equal to its WACC, then under all reasonable conditions the project's NPV must be zero.
D) There is no necessary relationship between a project's IRR, its WACC, and its NPV.
E) When evaluating mutually exclusive projects, those projects with relatively long lives will tend to have relatively high NPVs when the cost of capital is relatively high.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If the WACC is 10%, both projects will have positive NPVs.
B) If the WACC is 6%, Project S will have the higher NPV.
C) If the WACC is 13%, Project S will have the lower NPV.
D) If the WACC is 10%, both projects will have a negative NPV.
E) Project S's NPV is more sensitive to changes in WACC than Project L's.
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have the higher IRR at the new WACC.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 81 - 100 of 107
Related Exams