A) 2.16 years
B) 2.28 years
C) 2.02 years
D) 2.12 years
E) 2.00 years
Correct Answer
verified
Multiple Choice
A) $29.26
B) $23.11
C) $32.18
D) $32.77
E) $25.45
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the WACC,while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the risk-free rate,while the IRR method assumes reinvestment at the IRR.
C) The NPV method assumes that cash flows will be reinvested at the WACC,while the IRR method assumes reinvestment at the risk-free rate.
D) The NPV method does not consider all relevant cash flows,particularly cash flows beyond the payback period.
E) The IRR method does not consider all relevant cash flows,particularly cash flows beyond the payback period.
Correct Answer
verified
Multiple Choice
A) 11.48%
B) 10.57%
C) 13.05%
D) 15.00%
E) 14.35%
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B,then Project A must have the lower NPV.
B) If Project A has a higher IRR than Project B,then Project A must also have a higher NPV.
C) The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC.
D) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
E) If a project has normal cash flows and its IRR exceeds its WACC,then the project's NPV must be positive.
Correct Answer
verified
Multiple Choice
A) $34.24
B) $26.78
C) $33.90
D) $27.80
E) $25.77
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method versus the NPV is that the IRR does not take account of cash flows over a project's full life.
B) One defect of the IRR method versus the NPV is that the IRR does not take account of the time value of money.
C) One defect of the IRR method versus the NPV is that the IRR does not take account of the cost of capital.
D) One defect of the IRR method versus the NPV is that the IRR values a dollar received today the same as a dollar that will not be received until sometime in the future.
E) One defect of the IRR method versus the NPV is that the IRR does not take proper account of differences in the sizes of projects.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 14.11%
B) 15.52%
C) 15.81%
D) 10.72%
E) 17.22%
Correct Answer
verified
Multiple Choice
A) The shorter a project's payback period,the less desirable the project is normally considered to be by this criterion.
B) One drawback of the payback criterion is that this method does not take account of cash flows beyond the payback period.
C) If a project's payback is positive,then the project should be accepted because it must have a positive NPV.
D) The regular payback ignores cash flows beyond the payback period,but the discounted payback method overcomes this problem.
E) One drawback of the discounted payback is that this method does not consider the time value of money,while the regular payback overcomes this drawback.
Correct Answer
verified
Multiple Choice
A) If the WACC is 13%,Project A's NPV will be higher than Project B's.
B) If the WACC is 9%,Project A's NPV will be higher than Project B's.
C) If the WACC is 6%,Project B's NPV will be higher than Project A's.
D) If the WACC is greater than 14%,Project A's IRR will exceed Project B's.
E) If the WACC is 9%,Project B's NPV will be higher than Project A's.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV) ,then discounting the TV at the WACC.
B) The lower the WACC used to calculate it,the lower the calculated NPV will be.
C) If a project's NPV is less than zero,then its IRR must be less than the WACC.
D) If a project's NPV is greater than zero,then its IRR must be less than zero.
E) The NPV of a relatively low-risk project should be found using a relatively high WACC.
Correct Answer
verified
Multiple Choice
A) $119.30
B) $118.12
C) $113.40
D) $121.67
E) $135.84
Correct Answer
verified
Multiple Choice
A) The MIRR and NPV decision criteria can never conflict.
B) The IRR method can never be subject to the multiple IRR problem,while the MIRR method can be.
C) One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on a generally more reasonable reinvestment rate assumption.
D) The higher the WACC,the shorter the discounted payback period.
E) The MIRR method assumes that cash flows are reinvested at the crossover rate.
Correct Answer
verified
Showing 21 - 40 of 107
Related Exams